We are tantalisingly close to opening our new multi-purpose hall, and we’re so looking forward to showing it to you all.  But, for the moment, it’s still in the care of the builder and not yet open to the school.

Inevitably, we have had some delays – late delivery of materials at key moments, more onerous fire-retardant measures than anticipated, and improvements to the heating and air-conditioning systems.

We are nearly there now.  Delays over the past few months have affected some delivery slots for signage, sports equipment and line markings in the new building.  Full steam ahead, and we are getting there.  We want you to see the hall as a fully functioning building, complete with basketball hoops, basketball and volleyball court layouts, and all the rest of the things that make the building what it is!

At this stage, we are sure to start our next academic year this September with a fully functioning multi-purpose hall.  It will be worth the wait!